RB 5:Zawarcie umowy na budowę bloku energetycznego w Rybniku
Firma: PGE POLSKA GRUPA ENERGETYCZNA SPÓŁKA AKCYJNASpis treści:
1. RAPORT BIEŻĄCY
2. MESSAGE (ENGLISH VERSION)
3. INFORMACJE O PODMIOCIE
4. PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ
KOMISJA NADZORU FINANSOWEGO | ||||||||||||
| Raport bieżący nr | 5 | / | 2023 | ||||||||
Data sporządzenia: | 2023-02-09 | |||||||||||
Skrócona nazwa emitenta | ||||||||||||
PGE POLSKA GRUPA ENERGETYCZNA S.A. | ||||||||||||
Temat | ||||||||||||
Zawarcie umowy na budowę bloku energetycznego w Rybniku | ||||||||||||
Podstawa prawna | ||||||||||||
Art. 17 ust. 1 MAR - informacje poufne. | ||||||||||||
Treść raportu: | ||||||||||||
Zarząd spółki PGE Polska Grupa Energetyczna S.A. („PGE") informuje, że w dniu 9 lutego 2023 roku Rybnik 2050 sp. z o.o., spółka zależna od PGE, zawarła umowę („Umowa”) z konsorcjum firm w składzie: Polimex Mostostal S.A. (lider konsorcjum), Siemens Energy Sp. z o.o. (członek konsorcjum), Siemens Energy Global GmbH & Co. KG (członek konsorcjum) (łącznie zwanymi dalej „Wykonawcą"). Przedmiotem Umowy jest wykonanie przez Wykonawcę robót budowlano-montażowych oraz innych prac, w celu wybudowania bloku gazowo-parowego w Rybniku o znamionowej mocy elektrycznej brutto 882 MWe. Blok zostanie zrealizowany w technologii gazowo-parowej w układzie dwuwałowym. Zgodnie z zapisami Umowy, przekazanie do eksploatacji bloku ma nastąpić do dnia 31 grudnia 2026 r. Wartość Umowy wynosi 3 050 000 000,00 zł netto. W powiązaniu z Umową zawarta została ponadto umowa o świadczenie usług serwisowych dla turbiny gazowej przez okres minimum 12 lat od dnia przekazania bloku do eksploatacji. Wartość umowy serwisowej wynosi 762 484 777,60 zł netto. Łączna wartość wszystkich zawartych umów wynosi 3 812 484 777,60 zł netto. Umowa przewiduje kary umowne dla Wykonawcy związane m.in. z niedotrzymaniem terminu przekazania bloku do eksploatacji, niedotrzymaniem gwarantowanej mocy znamionowej bloku netto, niedotrzymaniem gwarantowanego poziomu dyspozycyjności oraz niedotrzymaniem gwarantowanej sprawności bloku netto. Łączna suma kar umownych, wynikających ze wszystkich tytułów przewidzianych Umową nie może przekroczyć 20% wartości netto Umowy. W przypadku odstąpienia od Umowy w całości lub w zakresie niewykonanej części z przyczyn, za które jedna ze stron ponosi odpowiedzialność zgodnie z Umową, druga strona jest uprawniona do obciążenia odpowiedzialnej strony karą umowną w wysokości 10% wartości Umowy. Umowa zawiera także klauzulę waloryzacyjną uwzględniającą potencjalne podwyższenie wynagrodzenia Wykonawcy o połowę skumulowanego wzrostu cen produkcji budowlano-montażowej publikowanego na stronie internetowej Głównego Urzędu Statystycznego. Maksymalna waloryzacja wynagrodzenia z tego tytułu nie może przekroczyć 15% wartości Umowy. |
MESSAGE (ENGLISH VERSION) | |||
Signing of the agreement for construction of the power unit in Rybnik
The Management Board of PGE Polska Grupa Energetyczna S.A. (”PGE") discloses that on February 9, 2023 Rybnik 2050 sp. z o.o., a subsidiary of PGE, signed an agreement (the ”Agreement”) with consortium of: Polimex Mostostal S.A. (consortium leader), Siemens Energy Sp. z o.o. (consortium member), Siemens Energy Global GmbH & Co. KG (consortium member) (jointly later referred to as the “Contractor").
The subject matter of the Agreement is the performance of construction and assembly works and other works by the Contractor, in order to build a gas and steam unit in Rybnik with a gross capacity of 882 MWe. The unit will be constructed in CCGT technology in two-stage system. According to the provisions of the Agreement, the commissioning of the unit will take place by December 31, 2026.
The value of the Agreement amounts to PLN 3 050 000 000.00 net. In connection with the Agreement, a service agreement was also signed with regard to gas turbine for the period of at least 12 years starting from the commissioning date of the unit. The value of the service agreement amounts to PLN 762 484 777.60 net. Total value of all signed agreements amounts to PLN 3 812 484 777.60 net.
The Agreement provides for contractual penalties for the Contractor related to, among others, failure to meet the deadline for commissioning of the unit, failure to comply with the guaranteed net rated capacity, failure to deliver the guaranteed level of availability and failure to meet guaranteed net efficiency of the unit.
The total sum of contractual penalties resulting from all failures cannot exceed 20% of the net value of the Agreement.
In case of withdrawal from the Agreement in full or in the scope of the unfulfilled part for reasons for which one of the parties is liable under the Agreement the other party is entitled to charge the responsible party with a contractual penalty in the amount of 10% of the value of the Agreement. The Agreement also includes an indexation clause which takes into account potential increase of the Contractor’s remuneration by half of the cumulative increase in the prices of construction and assembly production which are published on the website of the Central Statistical Office of Poland. The maximum indexation of the remuneration due to the above cannot exceed 15% of the Agreement’s value. |
PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ | |||||
Data | Imię i Nazwisko | Stanowisko/Funkcja | Podpis | ||
2023-02-09 | Lechosław Rojewski | Wiceprezes Zarząd | |||
2023-02-09 | Paweł Śliwa | Wiceprezes Zarządu |