ČEZ, a.s.: Zakup projektu 600MW farmy wiatraków w Rumunii (2008-08-27)

|
selectedselectedselected
Reklama
Aa
Udostępnij
facebook
twitter
linkedin
wykop

RB 154:CEZ kupuje projekt 600MW farmy wiatraków w Rumunii

Firma: CEZ, a.s.
Spis treści:
1. RAPORT BIEŻĄCY
2. MESSAGE (ENGLISH VERSION)
3. INFORMACJE O PODMIOCIE
4. PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ

KOMISJA NADZORU FINANSOWEGO









Raport bieżący nr 154 / 2008





Data sporządzenia: 2008-08-27
Skrócona nazwa emitenta
CEZ, a.s.
Temat
CEZ kupuje projekt 600MW farmy wiatraków w Rumunii
Podstawa prawna
Art. 56 ust. 1 pkt 2 Ustawy o ofercie - informacje bieżące i okresowe
Treść raportu:
Grupa ČEZ oraz spółka Continental Wind Partners LLC zawarły w dniu wczorajszym sprzedaż projektu sąsiadujących farm wiatraków Fontanele i Cogealac w Rumunii Grupie ČEZ. Projekt tych dwóch sąsiadujących farm wiatraków o całkowitej mocy zainstalowanej w wysokości 600 MW oznacza budowę największej przybrzeżnej farmy wiatraków w Europie. Zainstalowana moc projektu przekracza dwukrotnie moc drugiej największej europejskiej farmy wiatraków w budowie i osiąga trzykrotną zainstalowaną moc do tej pory eksploatowanej największej farmy wiatraków w Europie (Guadalajara, Hiszpania). Inwestycja Grupy ČEZ do tego projektu osiągnie 1,1 miliarda euro (ok. 27 miliard koron).

Miejscowości Fontanele i Cogealac znajdują się w rumuńskiej prowincji Dobrudża na północ od miasta Constanta w odległości 17 km od Morza Czarnego. Projekt będzie wprowadzany do eksplotacji stopniowo. Pierwsza faza projektu licząca 139 maszyn GE 2,5xl o całkowitej wydajności 347,5 MW zostanie wprowadzona do eksploatacji w roku 2009. Chodzi o typ elektrowni wiatrowej z wysokością 100 metrów i średnicą rotora 99 metrów. Druga faza projektu z mocą całkowitą 252,5 MW zostanie wprowadzona do eksplotacji rok później do końca roku 2010. Sama budowa parku wiatraków rozpocznie się w następnym miesiącu. Projekt jest umieszczony w maksymalnej trosce o środowisko naturalne, warunki wiatrowe w lokalizacji są doskonałe. Projekt farmy wiatraków będzie oznaczał prawie 30% udział w rumuńskim rynku energii ze źródeł odnawialnych (włącznie dużych elektrowni wodnych). Jest to pierwszy ważny projekt farmy wiatraków w Rumunii, dzisiejsza zainstalowana moc elektrowni wiatrowych w kraju wynosi tylko 7 MW.

"Niniejszy projekt wiatraków znacząco wzmocni pozycję Grupy ČEZ w Rumunii, rozszerzy nasze działania także w sektorze produkcji elektryczności. Projekt jest już całkowicie przygotowany, posiada wszystkie potrzebne zezwolenia, włącznie gwarantowanego przyłączenia do sieci, technologia dla pierwszej fazy jest także w pełni zapewniona umowami. Inwestycja do źródeł odnawialnych jest jednym z ogółu posunięć strategicznych, którymi reagujemy na zaproponowany pakiet energetyczno-klimatyczny UE. Pomimo tego w ramach obniżania emisji CO2 koncentrujemy się także na rozszerzeniu portfolia produkcyjnego o elektrownie gazowe i dalsze wykorzystanie elektrowni jądrowych,“ powiedział Martin Roman, Prezes Zarządu i Dyrektor Generalny ČEZ.

MESSAGE (ENGLISH VERSION)






CEZ Group Buys 600 Megawatt Wind Farm Project in Romania from
Continental Wind PartnersPrague, August 27, 2008 – Yesterday
evening, CEZ Group, the leading CE power utility, and Continental Wind
Partners LLC, a major renewable power developer, concluded the sale of
CWP’s adjacent Fantanele and Cogealac wind farms in Romania to CEZ. The
two projects will together be the largest onshore wind farm in Europe,
with a total capacity of 600 megawatts, approximately double the size of
the next largest fully permitted onshore wind farm in Europe, and triple
the size of the largest current operational wind farm in Europe. The
total investment of the CEZ Group into the project will reach € 1.1
billion.


Fantanele and Cogealac are situated in the Dobrogea province, north of
Constanta, about 17 kilometers from the Black Sea. The project will
become operational in stages. The first stage of 347.5 MW will comprise
139 GE 2.5xl turbines with a 100 meter hub height and 99 meter rotor
diameters and a 2.5 megawatt capacity and will be operational by end of
2009. The second stage of 252.5 MW will be operational by end 2010. The
construction will begin next month. Wind speeds are excellent, and the
project is carefully situated to minimize environmental impact. The
windfarm will represent almost 30% of the renewable market in Romania
(including large hydro) when it becomes fully operational. It is the
first significant wind project to be realized in Romania, which today
has only 7 MW of operational wind energy production.


”This wind farm project will strengthen the position of the CEZ Group in
Romania itself and enlarges our activities in the electricity generation
sector there. The project has all necessary licenses and permissions
including guaranteed connection to the grid and the hardware for the
first stage has already been fully contracted. Investment into
renewables is one of the strategic measures we are taking to respond to
the adopted energy-climatic package of the EU. In addition to that, we
are also concentrating on extending our production portfolio by gas
power plants and further nuclear power plants using as another way to
meet our targets of reducing CO2 emissions,” said Martin Roman,
Chairman of the Board and CEO of CEZ.


CWP will manage the construction of the wind farm, which will be built
by major international construction firms. All related technical
components of the project (transformers, cables, etc) are secured and
will arrive on site in time to commence operations according to
schedule.


Mark Crandall, Chairman and founder of CWP said “CWP has been very
excited about the potential of the Romanian market since it began
development here more than two years ago, and we are very pleased to
have found a partner in CEZ which shares our enthusiasm and excitement
about this extraordinary project and this extraordinary country –
nothing could give the management and shareholders of CWP more pleasure
than seeing this ground-breaking project be completed and seeing it
transform the Romanian market for renewable energy.”


Notes for Editors:


About Continental Wind Partners LLC


CWP was established in 2006 to finance the development of wind farms in
Romania and Poland. Since then it has expanded into other European
countries as well as Australia and New Zealand. CWP’s pipeline of
projects currently totals more than 4,500 megawatts of wind assets in
different stages of development and it continues to expand aggressively
through new partnerships with local developers.


CWP together with its local partners secures land rights, measures and
analyses wind resources, designs wind farms, obtains planning consents,
selects and procures turbines and other necessary equipment, studies the
environmental impact of potential sites, signs long-term sales contracts
for the electricity output, and accomplishes all the other tasks which
lead to the creation of a buildable wind farm.


For more information go to www.continentalwind.com


About CEZ


CEZ is the leading European utility with almost 7 million customers and
generation portfolio of 14 300 MW of installed capacity. Its market
capitalization exceeds 30 billion EUR. Its shares are traded on Prague
and Warsaw stock exchange. Apart from its home base in the Czech
Republic, the CEZ Group is active in 10 countries of Central and
Southeastern Europe (CSEE).


In Bulgaria, it owns the distribution and supply providing electricity
to 1.9 million customers and the largest hard-coal power plant in Varna.
In neighbouring Romania, it distributes and supplies power to 1.4
million customers. CEZ Group also owns two power generation companies in
Poland and actively trades electricity in all countries of CSEE. In
December 2007 CEZ and Hungarian oil and gas company MOL created
strategic alliance focusing on gas-fired power generation. Recently CEZ
in consortium with Turkish Akkök Group has won a tender for operation of
the Turkish distribution company Sedas.


More information available on www.cez.cz


PODPISY OSÓB REPREZENTUJĄCYCH SPÓŁKĘ
Data Imię i Nazwisko Stanowisko/Funkcja Podpis

Cena akcji Cez

Cena akcji Cez w momencie publikacji komunikatu to None PLN. Sprawdź ile kosztuje akcja Cez aktualnie.

W tej sekcji znajdziesz wszystkie komunikaty ESPI EBI Cez.

Jesteś dziennikarzem i szukasz pracy? Napisz do nas

Masz lekkie pióro? Interesujesz się gospodarką i finansami? Możliwe, że szukamy właśnie Ciebie.

Zgłoś swoją kandydaturę

Reklama